S.2498

From Swindon Panel Reference
Revision as of 20:30, 16 July 2014 by Danny (talk | contribs) (Text removed as moved to MAS Stage 1 page)
Jump to navigation Jump to search

Swindon MAS Stage 1 - Uffington to Highworth Junction

Back to list of Sources - Signalling Notices.

Download S.2498

This notice describes the first stage of the Swindon MAS scheme, planned to be introduced over the period Saturday 12th November to Monday 14th November 1966 between Uffington and Highworth Junction.

As part of this stage of the scheme, Knighton, Ashbury Crossing and Marston Crossing West Signal Boxes were all taken out of use, with all the signalling removed and the level crossings at Knighton and Ashbury temporarily closed pending conversion to AHB. Knighton Signal Box was planned to be taken out of use between 0700 and 0800 on Saturday 12th November, preliminary to the main occupation.

Full details of Stage 1 of the Swindon MAS Scheme.