This signal was planned to be converted to a controlled signal (from a semi-automatic), [[SN.18]], on 2 August 1970:
 
DM.70 was the protecting signal for Ashbury Level Crossing on the Down Main.
 
This signal was planned to be converted to a controlled signal ([[SN.18]]) (from a semi-automatic) on 2 August 1970:


[[File:SN_Won_AKOverton-1.jpg]]
[[File:SN_Won_AKOverton-1.jpg]]
Line 8: Line 11:


and the signal was actually converted to [[SN.18]] on 6 September of that year.
and the signal was actually converted to [[SN.18]] on 6 September of that year.
Latterly the signal was converted back to an automatic.

Revision as of 16:21, 5 August 2014

DM.70 was the protecting signal for Ashbury Level Crossing on the Down Main.

This signal was planned to be converted to a controlled signal (SN.18) (from a semi-automatic) on 2 August 1970:

SN Won AKOverton-1.jpg

But the work did not take place as planned:

SN Won AKOverton-2.jpg

and the signal was actually converted to SN.18 on 6 September of that year.