==First Attempt==
==First Attempt==


The signal was planned to be brought into use on 14 February 2000, as described in [[GWS.15]]. However, the work was not brought into use due to 'construction difficulties':
The signal was planned to be installed from 14 February 2000, but not brought into use, as described in [[GWS.15]]. However, the work was not completed due to 'construction difficulties':


[[File:WON-2000-03.png | border]]
[[File:WON-2000-03.png | border]]

Revision as of 12:40, 24 August 2014

Back to Control Functions.

This signal was newly installed in connection with the South Marston connection described in GWS.15 and GWS.27.

First Attempt

The signal was planned to be installed from 14 February 2000, but not brought into use, as described in GWS.15. However, the work was not completed due to 'construction difficulties':

WON-2000-03.png

Second Attempt

The signal was then planned to be brought into use on 18 January 2002.

WON-2002-02.png

and

WON-2002-03.png

but wasn't....

WON-2002-04.png