UM.75: Difference between revisions

From Swindon Panel Reference
Jump to navigation Jump to search
(Page created)
 
No edit summary
 
(2 intermediate revisions by the same user not shown)
Line 1: Line 1:
UM.75 became a controlled signal, [[SN.81]] at 0645 on Sudnay 11 June 2000.
Back to [[Control Functions]].


[[File:WON-2000-01.png]]
 
==Bridge Works==
 
During works on Stratton bridge (74m 75c) in 1975, an emergency replacement switch was fitted to this signal.
 
==Conversion to Controlled==
 
This signal was planned to be converted to a controlled signal, [[SN.81]], on 7 February 2000, as described in [[GWS.15]], but, due to 'construction difficulties' the work did not take place.
 
[[File:WON-2000-03.png | border]]
 
It was later converted at 0645 on Sunday 11 June 2000.
 
[[File:WON-2000-01.png | border]]

Latest revision as of 15:56, 9 November 2014

Back to Control Functions.


Bridge Works

During works on Stratton bridge (74m 75c) in 1975, an emergency replacement switch was fitted to this signal.

Conversion to Controlled

This signal was planned to be converted to a controlled signal, SN.81, on 7 February 2000, as described in GWS.15, but, due to 'construction difficulties' the work did not take place.

WON-2000-03.png

It was later converted at 0645 on Sunday 11 June 2000.

WON-2000-01.png