The signal was planned to be brought into use on 11 and 18 January 2002.
The signal was planned to be brought into use on 11 and 18 January 2002.


[[File:WON-2002-02.png | border]]
[[File:WON-2002-06.png | border]]


and
and

Latest revision as of 17:29, 24 August 2014

SN.899

Back to Control Functions.

This signal was newly installed in connection with the South Marston connection described in GWS.15 and GWS.27.

First Attempt

The signal was planned to be installed from 14 February 2000, but not brought into use, as described in GWS.15. However, the work was not completed due to 'construction difficulties':

WON-2000-03.png

Second Attempt

The signal was planned to be brought into use on 11 and 18 January 2002.

WON-2002-06.png

and

WON-2002-03.png

but wasn't....

WON-2002-04.png